Cut and Fill Calculator (Canada)

Site grading cut and fill from a grid of elevations in cubic metres and cubic yards, with swell for trucking and the Ontario rules for excess soil leaving a site.

The interactive tool loads here when JavaScript runs.

About this tool

What is the Cut and Fill Calculator?

Canadian grading plans are drawn in metres, but excavation and trucking are still often priced in cubic yards, so this version reports both. The default is a 40 by 30 metre commercial pad surveyed on a 10 metre grid with elevations from 209.3 to 210.6 m, graded to 209.80 m. The cut is 240.7 m³ and the fill 80.7 m³; after compaction and 25% swell, about 189 m³ (247 yd³) of loose material has to leave the site.

Where that soil goes is now regulated in Ontario. Under O. Reg. 406/19, On-Site and Excess Soil Management, a project in a settlement area that generates 2,000 m³ or more of excess soil must meet planning requirements, including a notice in the Excess Soil Registry before any soil leaves, assessments by a qualified person and a tracking system that follows each load. Projects on land most recently used for residential, agricultural, parkland or institutional purposes are generally outside that trigger, and other provinces have their own rules.

For balancing a site before you commit, adjust the pad elevation and watch the export figure change: each 0.1 m over 1,200 m² is 120 m³ of cut or fill.

  • Grid four-point method with split cut and fill cells
  • Average end area and prismoidal rules for cross-sections
  • Flat pad level or a full proposed grid
  • Swell, shrinkage and export or import balance in loose volume
  • Colour cell map, metric or imperial, copy and share
Read the guide: Cut and Fill Earthwork Volumes: Grid, End Area and Prismoidal

Updated

How to use the Cut and Fill Calculator

  1. Choose metres or feet and pick the method: grid levels, cross-sections or uniform depth.
  2. For a grid, paste existing levels as rows and columns, then enter a flat pad level or a proposed grid of the same shape and the grid spacing.
  3. For cross-sections, enter one line per station with the cut area and fill area.
  4. Set swell and shrinkage percentages from the soil report or typical values.
  5. Read cut, fill, net and the export or import volume in loose truck measure, and use the cell map to adjust the design level.

Worked examples

40 x 30 m pad at 209.80 m

Input

4 x 5 grid at 10 m, elevations 209.3 to 210.6 m, pad 209.80 m, swell 25%, shrinkage 10%

Output

Cut 240.7 m³ (314.8 yd³); fill 80.7 m³; export 188.8 m³ loose (246.9 yd³)

Fill needs 89.7 m³ of bank material after compaction, so 151 m³ of bank cut is surplus and swells to 188.8 m³ in the trucks.

Against the Ontario threshold

Input

Same pad, surplus 151 m³ bank

Output

Well under 2,000 m³ of excess soil

At this size the Registry planning requirements are not triggered, but the soil still has to go to a site that can lawfully accept it.

Background and insight

For a cell of plan area A whose four corners are all in cut or all in fill, the volume is A times the mean corner depth. Summed over a grid, every interior corner counts in up to four cells, which gives the textbook borrow-pit formula V = A/4 (Σh1 + 2Σh2 + 3Σh3 + 4Σh4). A cell that has both cut and fill corners is split with Vcut = A (Σc)² / (4 (Σc + Σf)) and Vfill = A (Σf)² / (4 (Σc + Σf)), where Σc and Σf are the corner depths in cut and fill as positive numbers. The two parts always net to A times the mean signed depth, so the net volume is exact for a planar cell.

Road earthwork is computed from cross-sections. The average end area method V = L (A1 + A2) / 2 is standard in highway practice and tends to overestimate when sections change shape quickly; the prismoidal formula V = L/6 (A1 + 4Am + A2) is exact for a prismoid, and with sections at equal spacing it becomes Simpson's rule. Bank (in-situ) soil swells when excavated, commonly 20 to 30% for common earth and more for rock, and shrinks below its bank volume when compacted in fill, often 10 to 20%. Balancing a site means comparing cut bank volume with fill divided by (1 - shrinkage), not raw cut with raw fill.

Common use cases

  • Building pads and slabs

    Find a pad level that balances cut and fill and avoids paying for import or disposal.

  • Road and track earthworks

    Total cut and fill between cross-sections along a centreline.

  • Pond and basin excavation

    Estimate the volume dug out and the trucks needed to remove it.

  • Checking contractor quantities

    Recompute volumes from the survey grid before agreeing a bill of quantities.

Tips and limitations

  • Strip and stockpile topsoil before grading; it is a separate quantity and not suitable as structural fill.
  • Swell for common earth is 20 to 30%; use the geotechnical report for anything large.
  • Truck capacities are usually quoted in cubic yards or tonnes; ask the hauler before turning volume into loads.

Sources and further reading

  1. Excess soil management and reuse requirements: project areas, Government of Ontario. O. Reg. 406/19 planning requirements, the 2,000 m³ trigger, the Excess Soil Registry and exemptions.
  2. Bringing excess soil to a reuse site, Government of Ontario

Frequently asked questions

How do I convert cubic metres of fill to cubic yards?

Multiply by 1.308. The calculator shows both: 240.7 m³ of cut is 314.8 yd³.

When does Ontario's excess soil regulation apply?

The planning requirements of O. Reg. 406/19 apply to projects generating 2,000 m³ or more of excess soil in a settlement area, and to enhanced investigation and remediation projects. Land most recently used for residential, agricultural, parkland or institutional purposes is generally excluded from the 2,000 m³ trigger.

What is the Excess Soil Registry?

An online registry where the project leader files a notice before any excess soil leaves a project that triggers the planning requirements, so loads can be tracked to the site that receives them.

How much does soil swell when excavated?

Common earth typically swells 20 to 30%, so 100 m³ in the ground fills about 125 m³ of truck space.

Why do I still need fill when cut is larger?

Compacted fill needs more than its own volume of bank material. At 10% shrinkage, 80.7 m³ of fill takes 89.7 m³ of cut.

Is there an in-depth guide to the Cut and Fill Calculator?

Yes. “Cut and Fill Earthwork Volumes: Grid, End Area and Prismoidal” covers the background, how it works, common pitfalls and worked examples. Read the full guide.