What is the Cut and Fill Calculator?

On a UK job the cut and fill sum usually ends in a muck away quote. Whatever you dig and cannot use on site is loaded into tippers or grab lorries and taken to a tip or a recycler, and the price depends on the loose volume, the weight and what the material is. This version starts with a small extension pad: a 12 by 8 metre area surveyed on a 4 metre grid, falling about 0.65 m across the plot, reduced to a formation level of 45.20 m.

That dig is 26.4 m³ in the ground. Allowing 25% bulking, the lorries carry 33 m³, which is the figure to give a muck away firm. Raising the formation to 45.40 m cuts the surplus to 6.9 m³ in the ground (8.6 m³ loose) because the low corner now needs a little fill, which is the kind of change worth testing before the levels are fixed.

Surplus soil that goes to landfill attracts landfill tax by the tonne. From 1 April 2026 the rates in England and Northern Ireland are £130.75 per tonne at the standard rate and £8.65 per tonne at the lower rate for qualifying inert material such as uncontaminated natural soil, which is why keeping soil on site, or sending clean soil to another site under the CL:AIRE Definition of Waste Code of Practice, is often cheaper than tipping it.

  • Grid four-point method with split cut and fill cells
  • Average end area and prismoidal rules for cross-sections
  • Flat pad level or a full proposed grid
  • Swell, shrinkage and export or import balance in loose volume
  • Colour cell map, metric or imperial, copy and share
Read the guide: Cut and Fill Earthwork Volumes: Grid, End Area and Prismoidal

Updated

How to use the Cut and Fill Calculator

  1. Choose metres or feet and pick the method: grid levels, cross-sections or uniform depth.
  2. For a grid, paste existing levels as rows and columns, then enter a flat pad level or a proposed grid of the same shape and the grid spacing.
  3. For cross-sections, enter one line per station with the cut area and fill area.
  4. Set swell and shrinkage percentages from the soil report or typical values.
  5. Read cut, fill, net and the export or import volume in loose truck measure, and use the cell map to adjust the design level.

Worked examples

Extension pad at 45.20 m

Input

3 x 4 grid at 4 m, levels 45.15 to 45.80 m, formation 45.20 m, bulking 25%, shrinkage 10%

Output

Cut 26.4 m³; fill 0.03 m³; muck away 33.0 m³ loose

Nearly all of it is surplus. Ask the muck away firm how they charge: by load, by tonne, or by the type of material on the transfer note.

Same pad raised to 45.40 m

Input

Same grid, formation 45.40 m

Output

Cut 9.9 m³; fill 2.7 m³; surplus 6.9 m³ in the ground, 8.6 m³ loose

Two hundred millimetres higher saves about 24 m³ of loose muck away, provided the finished floor, steps and drainage falls still work.

Background and insight

For a cell of plan area A whose four corners are all in cut or all in fill, the volume is A times the mean corner depth. Summed over a grid, every interior corner counts in up to four cells, which gives the textbook borrow-pit formula V = A/4 (Σh1 + 2Σh2 + 3Σh3 + 4Σh4). A cell that has both cut and fill corners is split with Vcut = A (Σc)² / (4 (Σc + Σf)) and Vfill = A (Σf)² / (4 (Σc + Σf)), where Σc and Σf are the corner depths in cut and fill as positive numbers. The two parts always net to A times the mean signed depth, so the net volume is exact for a planar cell.

Road earthwork is computed from cross-sections. The average end area method V = L (A1 + A2) / 2 is standard in highway practice and tends to overestimate when sections change shape quickly; the prismoidal formula V = L/6 (A1 + 4Am + A2) is exact for a prismoid, and with sections at equal spacing it becomes Simpson's rule. Bank (in-situ) soil swells when excavated, commonly 20 to 30% for common earth and more for rock, and shrinks below its bank volume when compacted in fill, often 10 to 20%. Balancing a site means comparing cut bank volume with fill divided by (1 - shrinkage), not raw cut with raw fill.

Common use cases

  • Building pads and slabs

    Find a pad level that balances cut and fill and avoids paying for import or disposal.

  • Road and track earthworks

    Total cut and fill between cross-sections along a centreline.

  • Pond and basin excavation

    Estimate the volume dug out and the trucks needed to remove it.

  • Checking contractor quantities

    Recompute volumes from the survey grid before agreeing a bill of quantities.

Tips and limitations

  • Strip and stockpile topsoil separately; it is a separate item on most quotes and is not suitable as structural fill.
  • Bulking of 20 to 30% is a reasonable start for clay and sandy soils. A site investigation report gives better figures for large jobs.
  • Muck away is usually quoted per load or per tonne, so ask the haulier what a tipper load holds for your type of soil before converting cubic metres to trips.
  • Waste transfer notes travel with each load of surplus soil, so keep them with the job file.

Sources and further reading

  1. Landfill Tax rates, HM Revenue and Customs. Standard rate £130.75 and lower rate £8.65 per tonne from 1 April 2026.
  2. Definition of Waste: Code of Practice (DoW CoP), CL:AIRE. Reuse of excavated materials on the site of origin, by direct transfer and within cluster projects.

Frequently asked questions

How do I work out muck away from a dig?

Calculate the dig volume in the ground (bank volume), subtract any of it you will reuse as fill, then add bulking, typically 20 to 30%, to get the loose volume the lorries carry. The calculator shows the loose surplus directly.

How much is landfill tax on soil?

In England and Northern Ireland, from 1 April 2026, landfill tax is £130.75 per tonne at the standard rate and £8.65 per tonne at the lower rate, which applies to qualifying materials such as uncontaminated natural soil and stones. Scotland and Wales set their own landfill taxes. The tax is charged by the landfill operator and passed on in the disposal price.

Can I reuse excavated soil on another site?

Often, if it is suitable and you follow the CL:AIRE Definition of Waste Code of Practice, which allows reuse on the site of origin, direct transfer of clean natural soil between sites and reuse within cluster projects without an environmental permit. Material reused outside a scheme like this is normally treated as waste.

What is a formation level?

The level of the prepared ground under the slab, sub-base or road build-up, not the finished surface. Take the build-up thickness off the finished level and use the result as the pad level in the calculator.

How accurate is a grid of levels for cut and fill?

Accurate enough for estimating if the grid catches every change of slope. The four-point method assumes the ground is a plane between survey points, so tighten the grid over banks and ditches.

Is there an in-depth guide to the Cut and Fill Calculator?

Yes. “Cut and Fill Earthwork Volumes: Grid, End Area and Prismoidal” covers the background, how it works, common pitfalls and worked examples. Read the full guide.