Cut and Fill Calculator (Australia)

Cut and fill volumes for a house pad on a sloping block from a grid of levels, with bulking, compaction and the NSW rules for reusing excavated natural material.

The interactive tool loads here when JavaScript runs.

About this tool

What is the Cut and Fill Calculator?

Much of the cut and fill work in Australia is a house pad on a sloping block: cut the high side, fill the low side and try to make the two balance so no truck has to come or go. This version starts with a 15 by 10 metre pad on a block falling 1.1 m across it, surveyed on a 5 metre grid. At a pad level of 51.85 m the cut and fill are both 17.1 m³, which looks balanced.

It is not quite. Fill has to be compacted, and compacted fill needs more than its own volume of cut soil: at 10% shrinkage the 17.1 m³ of fill takes 19.0 m³ of soil in the ground, so the pad is 1.9 m³ short, about 2.4 m³ loose. Dropping the pad to 51.60 m makes it a cut-only pad with 46.4 m³ of loose spoil to take away, which is the trade-off between a lower slab and the cost of a tipper.

Excavated soil that leaves the site becomes a waste question. In NSW, the EPA's excavated natural material order and exemption allow clean natural soil to be applied to other land as engineering fill or in earthworks, as long as the material meets the chemical and other requirements and records are kept for six years. Other states have their own rules for fill, so check with your state environment regulator before moving soil.

  • Grid four-point method with split cut and fill cells
  • Average end area and prismoidal rules for cross-sections
  • Flat pad level or a full proposed grid
  • Swell, shrinkage and export or import balance in loose volume
  • Colour cell map, metric or imperial, copy and share
Read the guide: Cut and Fill Earthwork Volumes: Grid, End Area and Prismoidal

Updated

How to use the Cut and Fill Calculator

  1. Choose metres or feet and pick the method: grid levels, cross-sections or uniform depth.
  2. For a grid, paste existing levels as rows and columns, then enter a flat pad level or a proposed grid of the same shape and the grid spacing.
  3. For cross-sections, enter one line per station with the cut area and fill area.
  4. Set swell and shrinkage percentages from the soil report or typical values.
  5. Read cut, fill, net and the export or import volume in loose truck measure, and use the cell map to adjust the design level.

Worked examples

Balanced pad on a sloping block

Input

3 x 4 grid at 5 m, levels 51.30 to 52.40 m, pad 51.85 m, bulking 25%, shrinkage 10%

Output

Cut 17.1 m³; fill 17.1 m³; short 1.9 m³ in the ground (2.4 m³ loose)

Equal cut and fill volumes never balance once compaction is counted. Lift the pad a little or plan a small import.

Same block, pad cut down to 51.60 m

Input

Same grid, pad 51.60 m

Output

Cut 41.0 m³; fill 3.5 m³; spoil to remove 46.4 m³ loose

A lower pad cuts into the high side and makes a taller cut batter or retaining wall, as well as the spoil to cart away.

Background and insight

For a cell of plan area A whose four corners are all in cut or all in fill, the volume is A times the mean corner depth. Summed over a grid, every interior corner counts in up to four cells, which gives the textbook borrow-pit formula V = A/4 (Σh1 + 2Σh2 + 3Σh3 + 4Σh4). A cell that has both cut and fill corners is split with Vcut = A (Σc)² / (4 (Σc + Σf)) and Vfill = A (Σf)² / (4 (Σc + Σf)), where Σc and Σf are the corner depths in cut and fill as positive numbers. The two parts always net to A times the mean signed depth, so the net volume is exact for a planar cell.

Road earthwork is computed from cross-sections. The average end area method V = L (A1 + A2) / 2 is standard in highway practice and tends to overestimate when sections change shape quickly; the prismoidal formula V = L/6 (A1 + 4Am + A2) is exact for a prismoid, and with sections at equal spacing it becomes Simpson's rule. Bank (in-situ) soil swells when excavated, commonly 20 to 30% for common earth and more for rock, and shrinks below its bank volume when compacted in fill, often 10 to 20%. Balancing a site means comparing cut bank volume with fill divided by (1 - shrinkage), not raw cut with raw fill.

Common use cases

  • Building pads and slabs

    Find a pad level that balances cut and fill and avoids paying for import or disposal.

  • Road and track earthworks

    Total cut and fill between cross-sections along a centreline.

  • Pond and basin excavation

    Estimate the volume dug out and the trucks needed to remove it.

  • Checking contractor quantities

    Recompute volumes from the survey grid before agreeing a bill of quantities.

Tips and limitations

  • Strip topsoil first and keep it for the garden; it is not suitable under a slab.
  • Allow for the slab and sand bed thickness: the pad level is the underside of the slab system, not the finished floor.
  • Ask the excavator how they price spoil removal and what a load holds before turning cubic metres into trips.
  • Cuts and fills near boundaries often need retaining walls and council approval; your council or state planning portal sets the limits.

Sources and further reading

  1. Resource recovery exemption: excavated natural material, NSW Environment Protection Authority. The excavated natural material exemption 2014: clauses 1.1 and 7.2 (applied to land as engineering fill or for use in earthworks) and 7.3 (the consumer keeps written records for six years).
  2. Current resource recovery orders and exemptions, NSW Environment Protection Authority. Lists the excavated natural material order and exemption of 21 November 2014 among the current orders and exemptions.

Frequently asked questions

How do I calculate cut and fill for a sloping block?

Take levels on a grid across the building platform, choose a pad level, and work out the depth of cut or fill at each point. The calculator sums each grid square, splits squares that change from cut to fill, and reports the cut, the fill and what is left over.

Why is my site short of fill when cut equals fill?

Because fill is compacted. With 10% shrinkage, 17.1 m³ of compacted fill needs 19.0 m³ of soil measured in the ground, so equal volumes leave you short.

Can I give my excavated soil to someone else as fill in NSW?

Only if it qualifies as excavated natural material under the NSW EPA order and exemption: it must meet the testing and chemical requirements, be applied to land as engineering fill or for earthworks, and the records must be kept for six years. Otherwise it is waste and must go to a lawful facility.

How much does soil bulk up when it is dug?

Common clays and loams typically bulk 20 to 30% when dug, rock far more. A geotechnical report for the block gives better figures if you have one.

What level should my house pad be?

Set by the design: the slab must sit above the finished ground for drainage and termite inspection zones, and below any height limits. Use the calculator to test a few pad levels and see how the earthworks change.

Is there an in-depth guide to the Cut and Fill Calculator?

Yes. “Cut and Fill Earthwork Volumes: Grid, End Area and Prismoidal” covers the background, how it works, common pitfalls and worked examples. Read the full guide.