India version. Volumes in cum from reduced levels, a plot-filling example, and the IS 1200 Part 1 rules Indian estimates and bills use for measurement, lead and lift. US version
Earthwork Cutting and Filling Calculator
Earthwork in cutting and filling from a grid of levels in cubic metres, with plot filling, borrow earth and the IS 1200 measurement rules for lead, lift and bulking.
The interactive tool loads here when JavaScript runs.
About this toolWhat is the Cut and Fill Calculator?
Indian estimates measure earthwork in cubic metres (cum) from reduced levels taken before and after, and IS 1200 Part 1 sets the rules: excavation is measured in the ground, "without allowance for increase in bulk", fill brought from a borrow pit is measured as excavation in the pit, and material measured in stacks gets an agreed deduction for voids. This calculator works the same way. Cut is the in-place volume, fill is the compacted volume, and the swell and shrinkage boxes turn them into truck loads and borrow quantities.
The default is a common case: a 15 m × 15 m plot (about 2,420 sq ft) sitting below the road, levelled on a 5 m grid with reduced levels from 99.80 to 100.45 m, to be filled up to 100.60 m before the plinth. That is 107.5 cum of compacted filling, which needs about 119.4 cum of earth measured in the borrow pit at 10% shrinkage, or roughly 149 cum loose in the tippers.
Lead and lift are measured separately. Under IS 1200 Part 1, lead is the shortest practicable distance for removal, counted in units of 50 m up to 250 m; lift is measured from ground level, with the first 1.5 m of depth included in the excavation item and extra lift in units of 1.5 m. Most schedules of rates price earthwork with a 50 m lead and 1.5 m lift included, so carriage beyond that becomes its own item.
- Grid four-point method with split cut and fill cells
- Average end area and prismoidal rules for cross-sections
- Flat pad level or a full proposed grid
- Swell, shrinkage and export or import balance in loose volume
- Colour cell map, metric or imperial, copy and share
Updated
How to use the Cut and Fill Calculator
- Choose metres or feet and pick the method: grid levels, cross-sections or uniform depth.
- For a grid, paste existing levels as rows and columns, then enter a flat pad level or a proposed grid of the same shape and the grid spacing.
- For cross-sections, enter one line per station with the cut area and fill area.
- Set swell and shrinkage percentages from the soil report or typical values.
- Read cut, fill, net and the export or import volume in loose truck measure, and use the cell map to adjust the design level.
Worked examples
Plot filling to 100.60 m
Input
4 × 4 grid at 5 m, levels 99.80 to 100.45 m, formation 100.60 m, swell 25%, shrinkage 10%
Output
Fill 107.5 cum; earth needed 119.4 cum in the borrow pit; about 149 cum loose
No cut at all, so every cum comes from outside. Bill the earth by measurement in the borrow area or by stacks with the voids deduction, as the contract specifies.
Same plot levelled at 100.15 m
Input
Same grid, formation 100.15 m
Output
Cutting 10.2 cum; filling 16.4 cum; import 8.1 cum in place
Lowering the formation nearly balances the site, but the plinth must still clear the road and the drain, so check levels before choosing.
Background and insight
For a cell of plan area A whose four corners are all in cut or all in fill, the volume is A times the mean corner depth. Summed over a grid, every interior corner counts in up to four cells, which gives the textbook borrow-pit formula V = A/4 (Σh1 + 2Σh2 + 3Σh3 + 4Σh4). A cell that has both cut and fill corners is split with Vcut = A (Σc)² / (4 (Σc + Σf)) and Vfill = A (Σf)² / (4 (Σc + Σf)), where Σc and Σf are the corner depths in cut and fill as positive numbers. The two parts always net to A times the mean signed depth, so the net volume is exact for a planar cell.
Road earthwork is computed from cross-sections. The average end area method V = L (A1 + A2) / 2 is standard in highway practice and tends to overestimate when sections change shape quickly; the prismoidal formula V = L/6 (A1 + 4Am + A2) is exact for a prismoid, and with sections at equal spacing it becomes Simpson's rule. Bank (in-situ) soil swells when excavated, commonly 20 to 30% for common earth and more for rock, and shrinks below its bank volume when compacted in fill, often 10 to 20%. Balancing a site means comparing cut bank volume with fill divided by (1 - shrinkage), not raw cut with raw fill.
Common use cases
Building pads and slabs
Find a pad level that balances cut and fill and avoids paying for import or disposal.
Road and track earthworks
Total cut and fill between cross-sections along a centreline.
Pond and basin excavation
Estimate the volume dug out and the trucks needed to remove it.
Checking contractor quantities
Recompute volumes from the survey grid before agreeing a bill of quantities.
Tips and limitations
- Take levels with an auto level or total station on a regular grid, and add points at every break in slope.
- Remove the top layer of vegetation and loose soil before measuring filling; it is not suitable fill.
- Fill in layers and compact each one with watering; the shrinkage figure assumes that is done.
- For trenches for pipes and cables, IS 1200 measures the authorised quantity or the quantity actually excavated, whichever is less, from cross-sections at suitable intervals, so use the cross-section method rather than a grid.
Sources and further reading
- IS 1200 (Part 1):1992 Methods of measurement of building and civil engineering works, Part 1 Earthwork, Bureau of Indian Standards (public copy). Clause 4.1 measurement without allowance for bulking; clause 5 lead and lift.
- Technical specifications for civil works (Part 2), State Bank of India. Earthwork items measured to IS 1200 with disposal within a 50 m lead.
Frequently asked questions
How is earthwork measured as per IS 1200?
In cubic metres, from the authorised dimensions of the excavation, without any allowance for bulking. Filling taken from a borrow pit is measured as excavation in the pit, and material in stacks is measured with a stated deduction for voids.
What are lead and lift in earthwork?
Lead is the horizontal distance the earth is carried, measured over the shortest practicable route in units of 50 m up to 250 m. Lift is the height it is raised, measured from ground level; the first 1.5 m is part of the excavation item and extra lift is paid in units of 1.5 m.
How much earth is needed to fill a plot?
Find the compacted fill volume from the levels, then divide by (1 − shrinkage). For a 15 m × 15 m plot raised to 100.60 m that is 107.5 cum compacted and 119.4 cum in the borrow pit at 10% shrinkage.
How do I calculate cutting and filling from reduced levels?
Subtract the formation level from each reduced level, then sum cell volumes as area times mean corner depth, splitting cells that change from cut to fill. Paste the levels as rows and the calculator does the rest.
What bulking factor should I use for earth?
Ordinary soil commonly bulks 20 to 30% when excavated; rock much more. Use figures from the soil report or past jobs on similar ground where you have them.
Is there an in-depth guide to the Cut and Fill Calculator?
Yes. “Cut and Fill Earthwork Volumes: Grid, End Area and Prismoidal” covers the background, how it works, common pitfalls and worked examples. Read the full guide.